Audio from Palmetto City Council was added on the Construcion Updates page.
Audio from Palmetto City Council Meeting 02/01/2010
February 11th, 2010Field Update from City Council
February 2nd, 2010Here is the current schedule as presented in tonight’s City Council Meeting:
23rd Street Design Completion: February 1, 2010
Bidding for 23rd Street: February 10, 2010
23rd Street Bid Opening: April 10, 2010
23rd Street Bid Award: May 10, 2010
Roadway Construction Commencement: July 10, 2010
Roadway Completion: December 10, 2010
Baseball Field Design Completion: May 10, 2010
Baseball Field Bidding: June 10, 2010
Bid Opening of Baseball Fields: August 10, 2010
Baseball Field Construction Commencement: September 10, 2010
Baseball Field and Amenity Completion: February 1, 2011