Field Update from City Council

February 2nd, 2010

Here is the current schedule as presented in tonight’s City Council Meeting:

23rd Street Design Completion:                       February 1, 2010

Bidding for 23rd Street:                                February 10, 2010

23rd Street Bid Opening:                                      April 10, 2010

23rd Street Bid Award:                                         May 10, 2010

Roadway Construction Commencement:           July 10, 2010

Roadway Completion:                                    December 10, 2010

 

Baseball Field Design Completion:                      May 10, 2010

Baseball Field Bidding:                                        June 10, 2010

Bid Opening of Baseball Fields:                          August 10, 2010

Baseball Field Construction Commencement:    September 10, 2010

Baseball Field and Amenity Completion:           February 1, 2011